Nomination Deadlines
Pre-month Nomination Timetable
| Business Days Prior to Beginning of Month |
Time |
Activity |
| 5 days |
10:30 am |
Pre-month noms for UGI Capacity are due |
| 3 days |
12:30 pm |
Pre-month noms for 3rd Party Capacity are due Pre-month split customer noms are due |
| 1 day |
12:30 pm |
Final contract numbers are due |
Daily Nomination Timetable for Next Day’s Flow
| Time |
Nom Type |
Activity |
| 10:30 am |
Combined |
Customer noms due for UGI Capacity |
| Split |
Supply noms due for UGI Capacity |
| 12:30 pm |
Combined |
Customer noms due for 3rd Party Capacity |
| Split |
Supply noms due for 3rd Party Capacity |
| 4:00 pm |
Split |
Customer noms due and must be balanced to supply noms |
- All times are Eastern Clock Time
- Nominations for Saturday, Sunday, and Monday must be received Friday by deadlines