When will UGI repair/repave the sidewalk in front of my property?

15 Apr 2018

If the sidewalk or street is disturbed and it is UGI’s responsibility to make final restoration (see above FAQ), UGI will immediately backfill it with sand and stone to avoid any safety hazards. We then need to wait a minimum of 90 days to allow for the settlement of materials before repairing the sidewalk or repaving the street. This work is also seasonal and cannot be completed in the late fall/winter months. Final repair/repaving can take three months to a year. Your safety is our top priority. If you identify any hazards, please contact UGI and we will expedite paving or repairs or redo the temporary paving or repair until permanent restoration can be done.